Tasks assigned to Ann
Item: Project scope approval meeting
Started Completed
Due Date: 11/19/2008 1/8/2009  
Status: Pushed from the 4th to the 19th because Toby was out of town.
Item: First draft of white paper
Started Completed
Due Date: 1/12/2009    
Status: Not yet started.
2 Tasks for Ann
Tasks assigned to Daisy
Item: Initial art work for marketing launch
Started Completed
Due Date: 11/4/2008    
Status: Waiting on final name
Item: Reserve space in Vegas trade show
Started Completed
Due Date: 12/12/2008
11/26/2008
 
Status: Not happy with the availalbe spaces. Working to upgrade
Item: Update website with customer success story
Started Completed
Due Date: 12/31/2008
 
 
Status: Not yet started
3 Tasks for Daisy
Tasks assigned to Greg
Item: Trademark search
Started Completed
Due Date: 11/12/2008
11/3/2008
11/14/2008
Status: Done
Item: Trademark application
Started Completed
Due Date: 11/7/2008
10/14/2008
1/17/2008
Status: Done
Item: Budget allocation meeting
Started Completed
Due Date: 11/17/2008 11/17/2008 11/17/2008
Status: Done
3 Tasks for Greg
Tasks assigned to Mark B.
Item: Create project scope documentation
Started Completed
Due Date: 11/4/2008 10/15/2008 10/31/2008
Status: Done
Item: Finalize specifications
Started Completed
Due Date: 12/4/2008 10/6/2008  
Status: Need to schedule meeting with Mark B and Toby to work through remaining issues.
Item: Customer sign off of specifications
Started Completed
Due Date: 12/4/2008    
Status: Waiting on final specs
Item: Get VP Approval for new resources
Started Completed
Due Date: 11/17/2008 11/10/2008  
Status: Submitted proposal 11/14. Waiting to hear back.
4 Tasks for Mark B.
Tasks assigned to Mark S.
Item: Marketing approval of new name
Started Completed
Due Date: 11/4/2008 11/3/2008  
Status: Sent to markting.  Working through red tape
Item: Schedule consumer focus group
Started Completed
Due Date: 11/21/2008 11/3/2008  
Status: Hired Swift Reasearch. In screening process.
2 Tasks for Mark S.
Tasks assigned to Mary
Item: Hire new resources
Started Completed
Due Date: 11/21/2008    
Status: On hold pending approval
1 Tasks for Mary
Tasks assigned to Toby
Item: Customer needs analysis
Started Completed
Due Date: 11/4/2008 9/25/2008 9/12/2008
Status: Done - See attached file.
Item: Risk analysis
Started Completed
Due Date: 12/12/2008 10/13/2008 10/17/2008
Status: Done
Item: Finalize project plan
Started Completed
Due Date: 11/12/2008 10/29/2008  
Status: First pass complete. Need to finalize completion dates
3 Tasks for Toby